Critical path analysis and linear programming
Practice Questions

6 CXC CAPE Applied Mathematics questions on Critical path analysis and linear programming, each with instant feedback and a full examiner-style mark scheme.

⚡ Start Quiz on Critical path analysis and linear programming →

Try 2 sample questions on Critical path analysis and linear programming

Question 1 · 1 mark · Difficulty 3/3

The longest path through a project network, determining the minimum completion time, is the:

  1. spanning tree
  2. cycle
  3. critical path
  4. shortest path
Show answer & explanation
✓ Answer: C — critical path
The critical path sets the minimum project time.
Question 2 · 1 mark · Difficulty 3/3

Activities on the critical path have zero:

  1. dependency
  2. float (slack)
  3. duration
  4. cost
Show answer & explanation
✓ Answer: B — float (slack)
Critical activities have no float.
⚡ Start a Quiz on Critical path analysis and linear programming →
20 questions · 25 min · free

CXC CAPE Applied Mathematics: Critical path analysis and linear programming FAQ

Is Kramizo free for CXC CAPE students preparing for Applied Mathematics?
Yes — completely free. Every student gets 45 questions a day on the free plan, with no card required and no trial countdown. That free quota works across every subject and every topic in our bank, so you can mix Critical path analysis and linear programming practice with other Applied Mathematics topics or even switch to a totally different CXC CAPE subject without paying anything. Kramizo's optional Pro plan removes the daily cap and adds detailed progress analytics, but the free tier is the real product — used by thousands of GCSE, IGCSE and CSEC students.
Are the Critical path analysis and linear programming questions aligned to the official CXC CAPE Applied Mathematics syllabus?
Every question is written against the published CXC CAPE Applied Mathematics specification, including the exact command words (state, describe, explain, calculate, evaluate, etc.), mark allocations, and difficulty tier you'd see on a real CXC CAPE paper. Explanations are written in the style of official examiner mark schemes — they tell you what is being awarded marks and why distractors are wrong, not just whether you got it right. The bank is continually refined to match the latest syllabus updates from CXC CAPE.
How is Critical path analysis and linear programming typically tested on CXC CAPE Applied Mathematics papers?
Critical path analysis and linear programming appears across multiple question types on real CXC CAPE Applied Mathematics papers — most commonly as multiple-choice questions in the objective section, structured short-answer questions in the main paper, and occasionally as part of an extended response. Kramizo's practice bank reflects that mix: 4-option MCQs, true/false statements, fill-in-the-blank key terms, multi-select questions, and ordering questions. Working through the bank gives you exposure to every question style examiners actually use.